66th Ave W Pavement Reconstruction Project
Project Description
The pavement reconstruction of 66th Ave W will address the existing poor pavement conditions while also improving pedestrian and bicycle facilities along the roadway. Significant street maintenance has not occurred since 2005 due to financial constraints and the pavement deterioration has accelerated over the past several years.
66th Ave W serves as one of two access points between the Premera campus (with over 2,000 employees) and the I-5/220th interchange, as well as surrounding light industrial/office park areas (MLT & Lynnwood). This roadway also provides access to the Snohomish County Southwest Recycling & Transfer Station, an essential public facility, which has contributed funds towards this project. In addition, the Interurban Trail crosses at the northern terminus of the roadway with non-ADA compliant curb ramps and no active warning devices. 66th Ave W is also part of the city's planned bicycle network to connect the trail to the 220th St SW commercial corridor and residential properties south of 220th.
Project Goal
The proposed project would reconstruct the pavement along this roadway, provide a narrowed Interurban Trail crossing with 2 ADA compliant curb ramps, active warning devices to improve trail user safety, and modify the roadway lane striping to provide two southbound vehicle travel lanes south of 216th St SW and one southbound lane north of 216th St SW. The project would also reconstruct 7 other non-compliant curb ramps throughout this segment to meet current ADA standards and extend fiber optic cabling and conduit north from 220th St SW to the 216th/66th traffic signal to incorporate it into the regional signal management system.
66th Ave W Project Interactive Map
Funding Sources
Washington State Transportation Improvement Board (TIB) -- $2,503,000
Snohomish County Recycling & Transfer Station -- $200,000
City of Mountlake Terrace Local Funds -- $878,298
Project Timeline
Design and Contract Document Preparation – 07/2020 to 05/2021
Construction start -- Fall 2023
Construction end – Summer 2024
News Releases
09/13/2023: Reconstruction Work to Start on 66th Ave W (PDF)