Paving on the Main Street project was wrapped-up October 11. This concluded the asphalt paving activity for this year. The final lift of pavement will be placed next spring when the weather warms up. The contractor striped new traffic lanes October 14 and shifted traffic to leave the sides of the street open for utility companies (Comcast, Wave, Frontier and Snohomish County PUD) to complete undergrounding work this winter.
The final large utility vault was installed Monday, October 21. No further roadway closures by the contractor are anticipated until spring activities.
For further information, contact Public Works Director Eric LaFrance at elafrance@ci.mlt.wa.us or (425) 744-6221.
###